Re: MRP basic scheduling for a group of materials

$
0
0

Dear,

 

If you want to consider the In house production time then you need to have MRP planning parameter as

Scheduling  = 2       Lead Time Scheduling and Capacity Planning.

 

If you want to exclude group of materials from MRP run then use exit M61X0001 FM EXIT_SAPMM61X_001 for MRP Run in MD01 for particular material group.

Refer below link for more info.

http://scn.sap.com/message/6627414#6627414

 

Regards,

R.Brahmankar