Hi Rahul,
All depends what you are after. I dont know of any document.
Some of our settings are for Block planning and discrete SNP optimizer, so a bit out of the box (instead of linear which is
the most common). A lot slower, and only needed if complex problems.
Do a lot of testing and see what works!
SNP PROFILE example
GEN TAB
Production capacity
Safety stock - take Absolute deviation
(tick) take period length
Ignore shelf life
DISCRETE CONSTRAINTS
Minimum PPM/PDS Lot Size 20 Z
Integral PPMs/PDS 20 Z
Sequence-Dependent Lot Size 20 Z
MODEL TAB
Average stock on hand
Bucket Offset During Production 1.00
Bucket Offset During Shipment 1.00
INTEGRATION
Dependent Demand for Fixed Orders Regard as hard constraint
Distribution Demand for Fixed Orders Regard as hard constraint
Substitution Demand for Fixed Orders Regard as hard constraint
Stock of Non-Selected PPM/PDS Input Products
Stock of not Selected Source Location Products
PPDS OPTIMIZER PROFILE eg
BASIC
Makespan 30.000000
Total Setup Times 10.000000
Total Setup Costs 30.000000
Maximum Delay Costs 10.000000
Total Delay Costs 10.000000
Late operations - schedule
ORDER PROCESS
Reschedule operations (scheduled and deallocated) ((To ensure get all operations))
validity period - regard as soft
HORIZON
Start - negative 1 month in the past
j